Building projects in Slakthusområdet

Slakthusområdet is the core of the City of Stockholm's Söderstaden: the old slaughterhouse district in Johanneshov is to hold around 3,000 homes and 14,000 workplaces by about 2035, with its own station on the metro's blue line from 2030. The 1910s halls are kept and given new uses while the blocks around them are built.

The facts are read from the City of Stockholm's, Region Stockholm's and the property owners' own pages, and each section shows when they were last checked.

New homes
3,000
New workplaces
14,000

Under way and coming

Individual buildings with a published timetable. The links go to the city's own project pages.

Parken Fållan

Park · Etapp 1 Fållankvarteren
City of Stockholm (Peab)

The town park of the first phase, between the new housing blocks and the metro's south entrance. The front part is open and the rest opens gradually during autumn 2026; landscaping began in June 2025 and the work is carried out entirely emission-free according to the city.

Complete November 2026● Opening soon

Hus 48 Lilla Marknadshallen

Offices · Slakthushallarna
Atrium Ljungberg

The 1912 market hall for small livestock, designed by Gustaf Wickman, is being restored inside and out into around 1,950 square metres of offices. Haglöfs is leasing 1,400 square metres for its head office and moves in in November 2026 according to the landlord's October 2025 press release.

Complete summer 2026, Haglöfs moves in autumn 2026● Opening soon

Tunnelbanestation Slakthusområdet

Infrastructure · Norra entrétorget och Centrala parken
Region Stockholm

The blue line's station with its platform 40 metres below ground, two exits and three entrances: the north one in a new office building at Arenavägen/Palmfeltsvägen near Tvärbanan, the south one level with 3Arena on Styckmästargatan with entrances towards Hallvägen and Slakthusgatan. Eight minutes to T-Centralen without changing, 19 escalators, art by Helena Isoz. When the station opens, Globen and Enskede gård close.

In other districts:The same blue line reaches Barkarbystaden and Barkarby in December 2027

Opens 2030● Under construction

Ombyggnaden av Arenavägen

Infrastructure · Arenavägen
City of Stockholm

Arenavägen is being lowered by up to a metre to meet the surrounding buildings and rebuilt as a city street, with extensive utility works beneath it, according to the city's page on ongoing works. Hallvägen has at the same time been opened all the way to Enskedevägen with a new junction, and the old entrance from Arenavägen to Hallvägen is closed for good.

August 2026 to mid-2029● Under construction

Hus 43 Gamla & Nya Magasinet

Offices · Slakthusområdet
Atrium Ljungberg

The 1930s warehouse is opened up with glazed gables and joined to a new building for around 8,500 square metres of offices, a 700 million kronor investment according to the landlord. Menigo moves its head office here in 2027 on around 3,800 square metres, together with Restaurangakademien.

Complete 2027● Under construction

Hus 25 Slakthushallarna

Offices · Hallgränd
Atrium Ljungberg

One of the original 1912 Art Nouveau halls, being converted into premises of 550–1,400 square metres with a private balcony over the concerts in Förbindelsehallen, according to the landlord's construction page.

Occupancy 2027● Under construction

P-hus Sandhagsgatan (mobilitetshus)

Infrastructure · Etapp 1 Fållankvarteren
Stockholm Parkering (NCC)

An underground mobility hub of 7,200 square metres with 250 car spaces, bicycle parking, a car pool and a pool of electric cargo bikes, according to Stockholm Parkering's own project page; construction started in autumn 2025 with NCC as contractor. On top, Sisab is to build a primary school – postponed, according to the city, since the pupils are not expected before the 2040s.

In other districts:Stockholm Parkering also plans Hjorthagsgaraget in Norra Djurgårdsstaden

Complete 2027● Under construction

Hus 06 Stationen

Offices · Rökerigatan
Atrium Ljungberg

The office building over the metro's north entrance: seven floors with 17,000 square metres of lettable space, six office floors of 2,400 square metres each, a restaurant and shops at the base and the station entrance inside the building, according to the landlord's construction page. The city's detailed plan 2D gained legal force in June 2022.

In other districts:Atrium Ljungberg also built Bas Barkarby in Barkarbystaden, opened 2022

Occupancy summer 2028● Under construction

Hus 23 Stockholms konstnärliga högskola

School · Premiärtorget, etapp 4A Evenemangskvarteren
Atrium Ljungberg, with SKH as tenant

Stockholm University of the Arts moves its whole operation into a new building by 3XN, winner of the 2022 architecture competition, with the first sod cut in June 2026 and a twenty-year lease. The building gets two large theatres, two cinemas, film studios and a circus hall with a 13-metre ceiling, and the school expects around 400 events a year. The block covers close to 36,000 square metres.

Occupancy summer 2030● Under construction

Ny hockeyarena i Globenområdet

Culture · Globenområdet
City of Stockholm

On 3 June 2026 the city presented plans for a new hockey arena for around 10,000 spectators to replace Hovet, on either Hovet's own site or the old Söderstadion site where the Söderhov housing plan stood. No construction start year is published. The arena is in Globenområdet, across Arenavägen.

○ Planned

Phases

The city's own phases for Slakthusområdet, with planning status, construction start, occupancy and unit counts. Finished phases come last.

Etapp 2D Tunnelbanekvarteret

2022–2030

Legal force June 2022; the station entrance 2022–2024, the building 2025–2027 with occupancy 2027; metro traffic start 2030

Atrium Ljungberg (office building with metro entrance); Region Stockholm (the station)

● Under construction

Etapp 4A Evenemangskvarteren

2025–2030

Legal force 10 January 2025; streets and squares 2025–2027; new buildings and squares complete 2030, when the university opens

Atrium Ljungberg (university of the arts, offices, retail and services; the office buildings seven to eight storeys)

● Under construction

Etapp 2A Kulturkvarteren

2027–2031

Approved by the planning committee 21 May 2026; adoption Q3 2026; construction start for streets, parks and squares Q1 2027; complete 2030/2031

Atrium Ljungberg (offices, hotel and premises), Corem, Sisab (the upper-secondary school); around 110,000 square metres of services, offices and school, of which 40,000 new

○ Planned

Etapp 2B Centrala kvarteren

2029–2031

Review 11 February–10 March 2026; adoption Q2 2027; construction start 2029; occupancy from 2031

John Mattson (rentals), Atrium Ljungberg, Lipid (condominiums), Castellum, Svenska Hus i Stockholm; seven preserved buildings, the 7,000-square-metre Centrala parken

around 450○ Planned

Etapp 3 Kylrumskvarteren

2028–2033

Review 12 March–8 April 2025; adoption Q1 2027; streets and parks 2028–2029; buildings 2028–2031; occupancy 2030–2033

Besqab (around 95 condominiums), Corem (around 121), Einar Mattsson (around 100 rentals), Micasa (care housing with around 100 flats and 28 senior homes), Selvaag Bostad (around 165), S:t Erik Markutveckling (offices)

around 650, including care housing and 28 senior homes○ Planned

Etapp 4C Arenakvarteren

Review 25 October–13 December 2023; approval Q1 2028, adoption Q2 2028

Castellum; SGA Fastigheter (3Arena). Three bridges: a foot and cycle bridge over Nynäsvägen and two footbridges over Arenavägen

○ Planned

Etapp 2E Norra entrékvarteren

Review 2027 at the earliest; adoption 2028 at the earliest; construction start for streets and squares 2030

Atrium Ljungberg (offices, hotel and premises); Norra entrétorget at Palmfeltsvägen/Arenavägen

○ Planned

Etapp 5A Parkhuskvarteren

Start memo December 2023; consultation Q2 2027; review Q2 2028; adoption Q2 2029

Atrium Ljungberg (homes and a preschool, land allocation 2019)

300–400○ Planned

Etapp 2C Gymnasiekvarteret

2024–2026

Legal force 1 December 2022; construction start June 2024; the school opened in the autumn term 2026

Atrium Ljungberg, with Sisab as tenant and Skanska as contractor

○ Completed

Source: City of Stockholm (vaxer.stockholm) · the city's page updated 2026-05-04

The development project also covers Globenområdet and Gullmarsplan–Nynäsvägen, which lie outside the area this directory covers. All of Söderstaden at the City of Stockholm

Already done in Slakthusområdet

The halls that have already reopened with new uses, and the new buildings that are finished, with the year each opened: the restaurant hall, the venues, the upper-secondary school and the park. Several of them are in the directory.

Hus 49 Stora Marknadshallen — Universal Music Group's offices
Gustaf Wickman 1912, one of the area's two market halls, blue-listed; occupied in early 2026 · opened 2026
Slakthusområdets gymnasium — Municipal upper-secondary school for 800 pupils, three programmes
Newly built in five storeys by Atrium Ljungberg with Skanska, for Sisab; opened August 2026 – Stockholm's first new municipal upper-secondary school in 40 years · opened 2026
Hus 01 Börshuset — Offices – A house Börshuset
Gustaf Wickman; once exchange and auction halls, bank, restaurant and telegraph station; opened as A house in February 2024 · opened 2024
Slakthallarna – Fållan, BAR15 och Förbindelsehallen — Concert and club halls from 50 to 3,500 people under the name Distriktfem
In the directory:Fållan · BAR15 · Förbindelsehallen
Art Nouveau halls from 1912; conversion began in 2020 and the halls opened permanently in April 2024 · opened 2024
Hus 26 Slakthushallarna — Restaurant and bar hall: Solen, Bar Montan, Hosoi, Dansken Slaktis, Matateljén, Stockholm Roast and Ateljéns Pizza
Gustaf Wickman 1912, Art Nouveau; reopened spring 2023 (Atrium Ljungberg) · opened 2023
Slakthuset, Slakthusgatan 6 — Nightclub on three levels with the rooftop Terrassen
In the directory:Slakthuset
The old slaughterhouse – the club opened in 2010 according to its own page · opened 2010

Source: Atrium Ljungberg (al.se) and the City of Stockholm

Every fact checked against the city's own pages on 2026-08-30 or later