The town park of the first phase, between the new housing blocks and the metro's south entrance. The front part is open and the rest opens gradually during autumn 2026; landscaping began in June 2025 and the work is carried out entirely emission-free according to the city.
Building projects in Slakthusområdet
Slakthusområdet is the core of the City of Stockholm's Söderstaden: the old slaughterhouse district in Johanneshov is to hold around 3,000 homes and 14,000 workplaces by about 2035, with its own station on the metro's blue line from 2030. The 1910s halls are kept and given new uses while the blocks around them are built.
The facts are read from the City of Stockholm's, Region Stockholm's and the property owners' own pages, and each section shows when they were last checked.
Under way and coming
Individual buildings with a published timetable. The links go to the city's own project pages.
The 1912 market hall for small livestock, designed by Gustaf Wickman, is being restored inside and out into around 1,950 square metres of offices. Haglöfs is leasing 1,400 square metres for its head office and moves in in November 2026 according to the landlord's October 2025 press release.
Tunnelbanestation Slakthusområdet
The blue line's station with its platform 40 metres below ground, two exits and three entrances: the north one in a new office building at Arenavägen/Palmfeltsvägen near Tvärbanan, the south one level with 3Arena on Styckmästargatan with entrances towards Hallvägen and Slakthusgatan. Eight minutes to T-Centralen without changing, 19 escalators, art by Helena Isoz. When the station opens, Globen and Enskede gård close.
In other districts:The same blue line reaches Barkarbystaden and Barkarby in December 2027
Arenavägen is being lowered by up to a metre to meet the surrounding buildings and rebuilt as a city street, with extensive utility works beneath it, according to the city's page on ongoing works. Hallvägen has at the same time been opened all the way to Enskedevägen with a new junction, and the old entrance from Arenavägen to Hallvägen is closed for good.
The 1930s warehouse is opened up with glazed gables and joined to a new building for around 8,500 square metres of offices, a 700 million kronor investment according to the landlord. Menigo moves its head office here in 2027 on around 3,800 square metres, together with Restaurangakademien.
One of the original 1912 Art Nouveau halls, being converted into premises of 550–1,400 square metres with a private balcony over the concerts in Förbindelsehallen, according to the landlord's construction page.
P-hus Sandhagsgatan (mobilitetshus)
An underground mobility hub of 7,200 square metres with 250 car spaces, bicycle parking, a car pool and a pool of electric cargo bikes, according to Stockholm Parkering's own project page; construction started in autumn 2025 with NCC as contractor. On top, Sisab is to build a primary school – postponed, according to the city, since the pupils are not expected before the 2040s.
In other districts:Stockholm Parkering also plans Hjorthagsgaraget in Norra Djurgårdsstaden
The office building over the metro's north entrance: seven floors with 17,000 square metres of lettable space, six office floors of 2,400 square metres each, a restaurant and shops at the base and the station entrance inside the building, according to the landlord's construction page. The city's detailed plan 2D gained legal force in June 2022.
In other districts:Atrium Ljungberg also built Bas Barkarby in Barkarbystaden, opened 2022
Hus 23 Stockholms konstnärliga högskola
Stockholm University of the Arts moves its whole operation into a new building by 3XN, winner of the 2022 architecture competition, with the first sod cut in June 2026 and a twenty-year lease. The building gets two large theatres, two cinemas, film studios and a circus hall with a 13-metre ceiling, and the school expects around 400 events a year. The block covers close to 36,000 square metres.
On 3 June 2026 the city presented plans for a new hockey arena for around 10,000 spectators to replace Hovet, on either Hovet's own site or the old Söderstadion site where the Söderhov housing plan stood. No construction start year is published. The arena is in Globenområdet, across Arenavägen.
Phases
The city's own phases for Slakthusområdet, with planning status, construction start, occupancy and unit counts. Finished phases come last.
Etapp 1 Fållankvarteren
Legal force 11 May 2021; construction start 2024; occupancy in phases from May 2026 to 2028
Besqab, Fastsam, Judiska Hemmet (80 care homes), K2A, Primula, Svenska Hem, Åke Sundvall, Atrium Ljungberg (offices and premises in four blocks), Stockholm Parkering
Etapp 2D Tunnelbanekvarteret
Legal force June 2022; the station entrance 2022–2024, the building 2025–2027 with occupancy 2027; metro traffic start 2030
Atrium Ljungberg (office building with metro entrance); Region Stockholm (the station)
Etapp 4A Evenemangskvarteren
Legal force 10 January 2025; streets and squares 2025–2027; new buildings and squares complete 2030, when the university opens
Atrium Ljungberg (university of the arts, offices, retail and services; the office buildings seven to eight storeys)
Etapp 2A Kulturkvarteren
Approved by the planning committee 21 May 2026; adoption Q3 2026; construction start for streets, parks and squares Q1 2027; complete 2030/2031
Atrium Ljungberg (offices, hotel and premises), Corem, Sisab (the upper-secondary school); around 110,000 square metres of services, offices and school, of which 40,000 new
Etapp 2B Centrala kvarteren
Review 11 February–10 March 2026; adoption Q2 2027; construction start 2029; occupancy from 2031
John Mattson (rentals), Atrium Ljungberg, Lipid (condominiums), Castellum, Svenska Hus i Stockholm; seven preserved buildings, the 7,000-square-metre Centrala parken
Review 12 March–8 April 2025; adoption Q1 2027; streets and parks 2028–2029; buildings 2028–2031; occupancy 2030–2033
Besqab (around 95 condominiums), Corem (around 121), Einar Mattsson (around 100 rentals), Micasa (care housing with around 100 flats and 28 senior homes), Selvaag Bostad (around 165), S:t Erik Markutveckling (offices)
Etapp 4C Arenakvarteren
Review 25 October–13 December 2023; approval Q1 2028, adoption Q2 2028
Castellum; SGA Fastigheter (3Arena). Three bridges: a foot and cycle bridge over Nynäsvägen and two footbridges over Arenavägen
Etapp 2E Norra entrékvarteren
Review 2027 at the earliest; adoption 2028 at the earliest; construction start for streets and squares 2030
Atrium Ljungberg (offices, hotel and premises); Norra entrétorget at Palmfeltsvägen/Arenavägen
Etapp 5A Parkhuskvarteren
Start memo December 2023; consultation Q2 2027; review Q2 2028; adoption Q2 2029
Atrium Ljungberg (homes and a preschool, land allocation 2019)
Etapp 2C Gymnasiekvarteret
Legal force 1 December 2022; construction start June 2024; the school opened in the autumn term 2026
Atrium Ljungberg, with Sisab as tenant and Skanska as contractor
Source: City of Stockholm (vaxer.stockholm) · the city's page updated 2026-05-04
The development project also covers Globenområdet and Gullmarsplan–Nynäsvägen, which lie outside the area this directory covers. All of Söderstaden at the City of Stockholm
Already done in Slakthusområdet
The halls that have already reopened with new uses, and the new buildings that are finished, with the year each opened: the restaurant hall, the venues, the upper-secondary school and the park. Several of them are in the directory.
Source: Atrium Ljungberg (al.se) and the City of Stockholm
Every fact checked against the city's own pages on 2026-08-30 or later